Vineyard Wind 1 Completes Turbine Installations, Overcoming Trump-Era Halt

Construction on Vineyard Wind 1, the first large-scale U.S. offshore wind farm and the first major project of its kind to reach completion during Donald Trump’s presidency, finished Friday night with installation of the final turbine blades south of Martha’s Vineyard, Massachusetts.pilotonline +1 The $4.5 billion, 800‑megawatt project’s 62 turbines are expected to ultimately power about 400,000 homes and cut 1.6 million metric tons of CO2 annually.ecoticias +1
The build-out wrapped up after a tumultuous nine-year journey that began with permit filings in 2017, stalled under federal review in 2019 and faced a late-stage stop‑work order from the Trump administration in December 2025, when the wind farm was 95% complete.pilotonline +1 A federal judge in Massachusetts cleared construction to resume in January 2026, rejecting the government’s national security rationale and allowing developers Avangrid and Copenhagen Infrastructure Partners to finish offshore work by March 14.virginiamercury +1
A Test Case for Courts, Presidents and “National Security” Claims
The Vineyard Wind fight turned into a high-profile clash over how far a president can go to halt privately financed clean‑energy projects that have already secured permits and sunk billions into construction. The Interior Department’s December 22, 2025 order paused five large East Coast offshore wind farms over unspecified national security risks, threatening projects worth tens of billions of dollars and prompting a wave of lawsuits from states and developers.utilitydive +1
In Vineyard Wind’s case, U.S. District Judge Brian E. Murphy ruled in late January that the administration had not shown an imminent security threat sufficient to justify shutting down a nearly finished, legally approved project, allowing work to resume on a farm that was reportedly losing about $2 million a day during the freeze.virginiamercury +1 The ruling followed similar defeats for the administration in cases involving Revolution Wind off Rhode Island and Connecticut, and Empire and Sunrise Wind off New York, leaving the government 0‑for‑4 in court as it continues to appeal.selc +1 Legal scholars said the string of injunctions signaled that courts expect more concrete evidence when national security is cited to override existing energy approvals.nationalinterest
What Vineyard Wind Means for U.S. Offshore Wind’s Future
With 62 GE Haliade‑X turbines installed roughly 15 miles south of Martha’s Vineyard and Nantucket, Vineyard Wind 1 is a proof‑of‑concept that the U.S. can build commercial‑scale offshore wind projects and assemble the complex supply chains they require.ecoticias +1 The wind farm relied on the $150 million New Bedford Marine Commerce Terminal as its staging port and employed about 3,500 workers during construction, according to Massachusetts officials.sierraclub Gov. Maura Healey has said the project is expected to save state ratepayers roughly $1.4 billion over its first 20 years of operation, even after a 2024 turbine‑blade failure led to a $10.5 million settlement with GE Vernova for business damages on Nantucket.sierraclub +1
Supporters in New England have framed the completion as a critical step toward meeting climate mandates and easing winter strain on the regional grid. “The completion of this project is essential to ensuring the state can lower costs, meet rising energy demand, advance its climate goals and sustain thousands of good-paying jobs,” Massachusetts Attorney General Andrea Joy Campbell said in a statement.pilotonline Industry groups argue that Vineyard Wind, combined with projects like Revolution Wind that are expected to reach full operation in 2026, undercuts claims that offshore wind is inherently unreliable or unbuildable at scale.boem +1
The Bigger Picture
Vineyard Wind’s finish line underscored a paradox: the first major offshore wind farm to be completed under a president who has repeatedly vowed to block such projects has instead become a showcase for how courts, states and private capital can keep the sector moving. The episode has also laid bare the political and regulatory risks that hang over U.S. offshore wind, even as it gains technical momentum. Whether investors continue to back multi‑billion‑dollar arrays up and down the East Coast may now hinge on how quickly remaining lawsuits are resolved, how future administrations handle “national security” objections—and whether Vineyard Wind’s turbines quietly delivering power to 400,000 homes can shift the politics of wind at sea.
pilotonline Los Angeles Times; sierraclub WBUR; ecoticias Vineyard Wind; boem reNews; virginiamercury New York Times; nationalinterest Utility Dive; utilitydive New York Times (Dec. 22, 2025 pause); vpm PBS NewsHour; bayjournal MassLive; selc CT Mirror / NYT on Revolution Wind; gcaptain PBS NewsHour on New York project; vpm New Bedford Light.
Sources
pilotonline
Column: Virginia’s future depends on clean energy solutions
The suspension of the Coastal Virginia Offshore Wind project is very worrisome. Virginia needs to bring much more renewable energy online to...
sierraclub
The Largest US Offshore Wind Project Is Ready to Go Despite Trump’s Vendetta
The largest offshore wind project in the United States is set to be completed on time—a win for an industry that has faced uncertainty under the...
ecoticias
2.6 million kW hidden offshore — U.S. ocean project to power 660,000 homes by 2026
Construction on the Coastal Virginia Offshore Wind (CVOW) project will take place on land and at sea. In 2026, 176 turbines will start to...
boem
Coastal Virginia Offshore Wind Project (CVOW) Research Project
In 2020, installation was completed on the first wind turbines installed in U.S. Federal waters. The offshore wind project has been fully operational since...
virginiamercury
Dominion offshore wind project paused over cited national security concerns
Interior Department orders 90-day halt as the utility company warns delay could strain grid reliability.
nationalinterest
Harnessing Nature’s Breath: The (Offshore) Wind Industry That Drives Green Power Forward
The offshore wind industry has been shaken up due to a pause on new leasing and permitting for new projects, but a significant amount of generating capacity...
utilitydive
Dominion says largest US offshore wind project on track
The 2.6-GW Coastal Virginia Offshore Wind project is set for completion by the end of 2026 despite vessel delays, the utility company said...
vpm
Dominion plans to complete Coastal Virginia Offshore Wind project in late 2026
The $9.8-billion Coastal Virginia Offshore Wind project will include 176 turbines stretching as far as 42 miles off the Virginia Beach coast.
bayjournal
Tariffs raise cost of Virginia offshore wind project by at least $506M
Virginia's offshore wind project has avoided obstacles posed by President Trump's order to cancel some offshore wind leases, but it has not...
selc
Customer protections a requirement for offshore wind in Virginia
Virginia is poised to continue its leadership on offshore wind, with the State Corporation Commission recently approving Dominion Energy's...
gcaptain
Turbine Installation Begins at Coastal Virginia Offshore Wind Farm After Court Lifts Federal Halt
Turbine installation has kicked off at the nation's largest offshore wind project just days after a federal judge lifted the Trump...
vpm
Dominion Energy says Virginia Beach wind farm's cost is up
The cost of building the nation's largest offshore wind farm off the Virginia Beach coast has jumped by nearly 10% since the original budget.
workboat
Dominion Energy says performance guarantee could kill Virginia offshore wind
Dominion Energy says its $9.8 billion Coastal Virginia Offshore Wind project – the largest in US waters to date – is in mortal danger if a performance...
utilitydive
BOEM approves 2.6-GW Dominion Energy offshore wind farm, largest yet in US
While other offshore wind developers have canceled PPAs and projects citing rising costs, Dominion Energy says the Virginia project is on...
prnewswire
Dominion Energy Completes Construction of First Offshore Wind Project in U.S. Federal Waters
Dominion Energy announced today the successful installation of the two turbine, 12-megawatt Coastal Virginia Offshore Wind (CVOW) pilot project 27 miles off...
windpowermonthly
Dominion set to avoid ‘performance guarantee’ for 2.6GW Virginia offshore wind
Dominion Energy has reached a settlement with the Virginia attorney general's office and other parties regarding rules for the construction cost and...
latimes
Construction finishes on a major offshore wind farm, the first during Trump's tenure - Los Angeles Times
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage under Trump, who is strongly...
djournal
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
guardonline
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
wftv
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
ottumwacourier
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
tdtnews
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
msn
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage under Trump, who is strongly...
thederrick
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
weatherforddemocrat
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
goshennews
Construction finishes on a major offshore wind farm, the first during Trump's tenure
Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Donald Trump's...
nytimes
A Rhode Island Wind Farm Changed Their View. And Their Lives, for the Better.
Offshore turbines let Block Island shut down soot-spewing, earsplitting diesel generators. There were other benefits, too.
workboat
Ørsted to cut workforce by 25%
Offshore wind developer Ørsted says it will reduce its workforce by 25% by the end of 2027, foreseeing a decline in new construction...
providencejournal
Fine, we'll give in: Here's a look at what was happening in RI in 2016
CIANCI DIED: Buddy Cianci, Providence's longest-serving mayor who helped rebuild "his" city and, despite serving five years for corruption,...
northeastern
Researchers measure impact of wind reductions on wind farm energy production
Researchers have conducted a study on Block Island Wind Farm to find out what impact turbulence has on production capabilities.
wbur
Nation's First Offshore Wind Farm To Start Spinning Soon Off Rhode Island
The five-turbine Block Island Wind Farm will harvest just a modest amount of the region's offshore wind potential.
stonybrook
Stony Brook Team Gets Up-Close Look at the Future of Offshore Wind Energy
In 2016, the five diesel generators that powered Block Island, Rhode Island, were replaced by five offshore wind turbines, making the area...
providencejournal
Offshore wind delivered hope for a clean energy future. What's next for RI isn't so clear
LINCOLN – When Josiah Bushway started his first day of training to do offshore construction, he didn't know if a job he'd lined up to help...
njspotlightnews
NJ offshore wind development dealt blow by EPA
The EPA has pulled an air permit for the Atlantic Shores project, citing President Trump's executive order pausing offshore wind projects.
nrel
Growth in Offshore Wind Energy Offers Huge Opportunity To Create U.S. Jobs
In the smallest town in the country's smallest state, something big has happened. In 2016, the residents of Block Island, a 7-mile-long and...
insideclimatenews
Only Permitted Great Lakes Offshore Wind Farm Put on Hold
The Department of Energy is revoking $37 million previously awarded to the six-turbine Icebreaker wind project, which has been in the works since 2009.
latimes
Letters to the Editor: Iran isn’t going to give Trump the unconditional surrender he wants
'The president has only created a war that our grandchildren and their grandchildren will likely be fighting for years to come,' writes an...
latimes
Trump administration to appeal offshore wind farm rulings
The Trump administration plans to appeal a series of court rulings blocking efforts to stop construction of offshore wind farms,...
latimes
Trump administration pauses 5 wind projects off the East Coast - Los Angeles Times
The Trump administration is suspending leases for five large-scale offshore wind projects under construction on the East Coast due to what...
latimes
Commentary: Those job numbers tell us that Trump's economy really stinks
A huge loss in jobs is a reminder that Trump's policies have stifled economic growth all year, and the Iran war will only make things worse.
latimes
Letters to the Editor: In halting offshore wind projects, we hinder our own clean energy potential
'President Trump's war against renewable energy sources is hurting Americans while lining the pockets of the oil industry,' writes an L.A....
latimes
Trump administration cites national security as it halts offshore wind. Some experts aren’t convinced
The U.S. Interior Department paused all work on large-scale wind projects under construction in the United States, citing national security.
latimes
Offshore wind developer prevails in court as Trump says U.S. 'will not approve any windmills'
A federal judge ruled Monday that work on an offshore wind farm for Rhode Island and Connecticut can resume even as President Trump seeks to...
albertmohler
Thursday, March 12, 2026
It's Thursday, March 12, 2026. I'm Albert Mohler, and this is The Briefing, a daily analysis of news and events from a Christian worldview.
latimes
Yet another judge rejects Trump effort to block offshore wind, saying N.Y. project can resume
A federal judge has ruled that an offshore wind project aimed at powering 600000 New York homes can resume construction.
wbur
Vineyard Wind, country's first large-scale offshore wind project, finishes construction
After years of starts and stops, construction on Vineyard Wind, the country's first large-scale offshore wind project, wrapped up this week.
mvtimes
Vineyard Wind construction nears completion
Iberdrola officials announced to investors last week that construction of Vineyard Wind 1, the offshore wind project located 15 miles south...
capecodtimes
Feds push to keep Vineyard Wind paused as 10 turbines stand bladeless
Federal officials on Jan. 21 asked a Massachusetts court to uphold the government's halt to construction at Vineyard Wind 1's offshore...
nytimes
Judge Revives Wind Farm That Trump Halted Off Martha’s Vineyard
The project, known as Vineyard Wind, was already 95 percent complete when the Trump administration ordered construction to stop.
newbedfordlight
Federal judge allows Vineyard Wind to resume construction
The ruling deals another blow to the Trump administration, which is now 0 for 4 in court battles over five suspended offshore wind projects.
vineyardgazette
Vineyard Wind Fights Construction Ban in Court
Vineyard Wind has now joined the legal battle against the Trump administration with a lawsuit that calls the stop work order placed on...
offshorewind
Court Clears 95-Pct-Complete Vineyard Wind 1 to Resume Construction
Construction work can restart on the 95-per-cent-complete Vineyard Wind 1 offshore wind farm after the US District Court for the District of...
electrek
Sunrise Wind is back, collapsing Trump’s offshore wind shutdown [update]
A federal judge allowed Sunrise Wind to resume construction, making it the fifth and final offshore wind project to beat the shutdown order.
masslive
‘95% complete’: Vineyard Wind 1 sues Trump admin. over halted offshore wind lease
The Massachusetts offshore wind project is 95% complete with 61 of 62 turbines built and is losing $2 million per day during the halt,...
newbedfordlight
Offshore wind power contracts delayed, again, to 2026
SouthCoast Wind and New England Wind have been stalled by the Trump administration's freeze of new offshore wind permits.
reuters
US offshore wind projects facing inflation headwinds
Soaring costs from rising inflation, interest rate hikes and supply chain delays cast doubts on U.S. President Joe Biden administration's...
oedigital
Offshore Wind: US Shipbuilders Answering the Call
It's a big deal when a U.S. president visits an American shipyard, and these trips always send a message. When President…
independent
70th Anniversary: Osinbajo, Tai Solarin, Wife, Others To Be Honoured At Mayflower School Founder’s Day
Former Vice President, Yemi Osinbajo, the late Dr. Tai Solarin and his wife, Sheila, tops the list of dignitaries to receive honour at the...
renews
Vineyard complete, Revolution delivers first power
CIP and Iberdrola have completed turbine installation at the 800MW Vineyard Wind 1 off the US while Orsted and Skyborn have delivered first...
ctmirror
Work can again resume on Revolution Wind, judge orders in blow to Trump
Judge Royce Lamberth ruled from the bench Monday that evidence provided by the federal government was not sufficient to justify halting...
nytimes
Judge Strikes Down Trump’s Latest Effort to Stop Offshore Wind Project
The ruling means that construction can continue on Revolution Wind, a $6.2 billion project off the coast of Rhode Island, at least for now.
npr
Offshore wind developer prevails in U.S. court as Trump calls wind farms 'losers'
A federal judge ruled Monday that work on a major offshore wind farm can resume, handing the industry at least a temporary victory as...
rhodeislandcurrent
Revolution Wind developers seek second court order against Trump administration
Revolution Wind developers are asking a federal judge to bar the Trump administration from suspending work on the already 87% completed...
mainepublic
With court backing, Revolution Wind appears headed for a 2026 finish
The new court showdown comes a few months after another federal ruling allowed Revolution Wind to resume construction. In September, Judge Royce...
bizjournals
Revolution Wind nears 'first power,' but Eversource not off the hook yet
Eversource expects to shed its last offshore wind liability once Revolution Wind reaches commercial operation later this year.
mvtimes
Offshore wind projects fight suspension orders
Just before Christmas, the administration of President Donald Trump halted work on all large-scale offshore wind projects under construction...
vineyardgazette
Judge Allows Revolution Wind to Restart Construction
In U.S. District Court in Washington, D.C. on Monday, Judge Royce Lamberth granted Revolution Wind a preliminary injunction against the stop...
providencejournal
Revolution Wind again wins federal court order lifting stop-work order
A federal judge has ruled for a second time in Revoution Wind's favor, lifting a stop-work imposed by the Trump administration.
bizjournals
Two New England offshore wind farms hit new milestones
New England's offshore wind industry celebrated Friday as Vineyard Wind 1 finished construction and the neighboring Revolution Wind...
newbedfordlight
Our offshore wind tracker: What’s new with wind projects off Massachusetts and beyond?
Offshore wind is changing fast. Here's our tracker, first published in April 2025, and the latest on where the Northeast's wind projects...
capecodtimes
Mass. offshore wind contract timeline slips amidst ‘ongoing uncertainty’
The offshore wind timeline just moved again. What's behind the delay, and what happens next.
wbur
What's up with offshore wind in New England? Here's a map
The Trump administration is bringing big changes to the U.S. offshore wind industry. Use this map to help keep track of where projects in...
rhodeislandcurrent
Trump orders Revolution Wind developers to stop offshore project already 80% complete
The Trump administration on Friday ordered developers of Rhode Island's first large-scale offshore wind farm to stop construction.
mainemorningstar
RI wind project was heading toward finish line. Now it’s about to veer into Boston federal court.
Fate of R.I. union workers, environmental mandates and energy grid hinge on multistate lawsuit against Trump administration...
renews
Next Massachusetts solicitation delayed until 2026
Massachusetts officials have delayed the fifth round of offshore wind procurement for the state until at least next year.
rtoinsider
New England OSW Contracts Delayed Again
New England's offshore wind ambitions were dealt a further setback as contract negotiations under way for most of the past year were extended again,...
renewablesnow
Massachusetts holds off on next offshore wind tender till at least 2026
Massachusetts will postpone launching its fifth offshore wind solicitation until at least 2026 due to federal uncertainty and delays in...
offshorewind
Massachusetts Postpones Round 5 Offshore Wind Solicitation
Massachusetts Department of Energy Resources (DOER) does not expect the Round 5 Request for Proposals (RFP) for offshore wind to be issued...
iberdrola
Vineyard Wind 1, our first offshore wind farm in the United States
Vineyard Wind 1 offshore wind farm, located off the coast of the state of Massachusetts (United States), will have a capacity of 800 MW.
capecodtimes
Nantucket reaches deal on Vineyard Wind transparency, response
After months of talks, Nantucket and Vineyard Wind have shaken hands on new rules for oversight, transparency and public involvement.
powermag
Vineyard Wind Delivers First Power to New England Grid
Copenhagen Infrastructure Partners (CIP) and Avangrid said the Vineyard Wind 1 offshore wind installation sent electricity to the power grid...
vineyardwind
Nation’s first commercial-scale offshore wind project
Vineyard Wind is currently building the nation's first utility-scale offshore wind energy project over 15 miles off the coast of Massachusetts.
offshorewind
Avangrid, CIP Secure USD 1.2 Billion in Capital for Vineyard Wind 1
CIP and Avangrid have secured a USD 1.2 billion first-of-its-kind tax equity package for the 800 MW Vineyard Wind 1 offshore wind project in the US.
renews
First turbine up at Vineyard Wind
Avangrid and Copenhagen Infrastructure Partners have installed the first GE Haliade-X wind turbine at their 800MW Vineyard Wind 1 project...
oedigital
Steel in the Water: Foundation Installation Kicks Off for First Commercial-scale U.S. Offshore Wind Farm
The installation of the first monopiles and transition pieces has kicked off for the first commercial-scale offshore wind…
inspenet
Vineyard Wind 1 offshore wind farm: cable laying began
Operations to install interconnection cables are about to begin at the Vineyard Wind 1 offshore wind farm.
powermag
In First for the U.S., Vineyard Wind Achieves $2.3B Financial Close for Offshore Wind Farm
Vineyard Wind 1, an 800-MW phase of an offshore wind project offshore Massachusetts, has achieved financial close. The milestone, a first...
reuters
Launch of US wind installation vessel masks critical shortage
Dominion Energy's 'Charybdis' will be the only American wind turbine installation vessel until markets soften and developers can justify the...
ctpublic
Vineyard Wind sues Trump administration for halting construction
Vineyard Wind, a large and nearly complete offshore wind farm near Massachusetts, says the Trump administration violated the law when it...
wbur
A progress report on Massachusetts' most controversial housing law
How much housing is in the pipeline due to the MBTA Communities Act? A new report from the think tank Boston Indicators takes a closer look.
bostonglobe
Do we really need two public radio stations in Boston?
Rather than cutting WBUR and GBH to the bone and seeing a decline in the quality of their programs, might it be wiser to merge the two...
wbur
Crews begin recovering sunken offshore wind blade off Nantucket
Crews started this week to retrieve and remove pieces of the shattered Vineyard Wind turbine blade that sunk to the ocean floor three months ago.
wbur
The 'Bitter' Tale Of The Budweiser Family
Budweiser, is known as the "King of Beers," and the Busch family was once considered practically royalty. Their early success led to a long...
canarymedia
Offshore wind farms race toward completion despite Trump’s attacks
Trump is trying to kill offshore wind. But two big East Coast projects are poised to start producing power, and others are hitting key...
ieefa
Offshore wind stop-work orders are costing consumers, delaying needed electricity
Efforts to stop five large offshore wind projects under construction along the Atlantic Coast could cost consumers billions of dollars and...
vineyardgazette
Government Halts All Offshore Wind Leases Over Security Concerns
The Trump administration announced Monday that it is pausing the leases for several offshore wind energy projects under construction south...
nytimes
Trump Halts 5 Wind Farms Off the East Coast
The Interior Department said the projects posed national security risks, without providing details. The decision imperils billions of...
ctmirror
Trump administration halts CT offshore wind project
Revolution Wind has created about 1200 direct jobs in CT and Rhode Island and would generate power to the equivalent of about 350000 homes.
mvtimes
Price tag for new high school at an estimated $333 million
Updated Dec. 22. The estimated cost and town-by-town breakdown for the new high school renovation and addition was announced as a staggering...
bostonglobe
Warren, Markey say Trump’s policies cost state $8.6 billion in clean energy funding and more than 16,000 jobs
A report from Senator Elizabeth Warren's and Senator Ed Markey's offices, released Tuesday, shows the state ranks second in lost or delayed...
canarymedia
Trump admin halts construction of nearly finished offshore wind farm
Ørsted's Revolution Wind project off the coast of Massachusetts and Rhode Island is hit with a stop-work order over vague "national...
newbedfordlight
Trump’s war on offshore wind: Tracking the actions and impacts
The Trump administration's actions – which have cost the wind industry hundreds of millions of dollars – are the focus of a lawsuit...
nbcboston
Construction finishes on major Mass. offshore wind farm — first during Trump's tenure
Vineyard Wind finished offshore construction with the final blades installed. The 62-turbine project will generate a total of 800 megawatts.
mvtimes
Vineyard Wind responds to lighting system complaints
Updated Aug. 6. Days after hearing from a heated Nantucket select board, Vineyard Wind announced Friday that it has integrated all of its...
newbedfordlight
How many homes does an offshore wind farm actually power?
Several readers have asked The Light about capacity factor and homes powered by wind projects. Here's a breakdown — and the math.
wgbh
An up-close look at Vineyard Wind, the nation's largest offshore wind project
The nation's largest offshore wind energy project is not easy to get a good look at. Vineyard Windis 15 miles off Martha's Vineyard and...
vineyardgazette
Wind Projects Make Headway
Offshore wind energy projects continue to progress in the waters south of the Vineyard, with two new wind farms approved and construction starting on a third.
boem
New England Wind 1 and 2
What's New? Construction and Operations Plan Approval. On July 1, 2024, BOEM announced its approval of the New England Wind Construction and Operations Plan...
capecodtimes
'A lot of people are upset.' Vineyard Wind compensation offer for fishermen stirs worries
Commercial fishers who are sharing part of their customary fishing waters with Vineyard Wind may be eligible for compensation.
oceanstatemedia
Are 17 Turbines Really Running at Vineyard Wind? Here’s What We Saw by Boat
A visit to Vineyard Wind 1 raises questions about the company's claims, with far fewer turbines spinning than reported and little...
dredgewire
Final Turbine Blades for Vineyard Wind 1 Leave for Site South of Martha’s Vineyard
Key Points. The Vineyard Wind 1 offshore wind project is closer to being finished, after the final turbine blades were shipped out of New...
pbs
Trump's offshore wind project freeze hit with lawsuits from states and developers
The Norwegian company Equinor and the Danish energy company Orsted are the latest to challenge the suspension order.
capecodtimes
Vineyard Wind stays silent as other East Coast offshore wind developers file lawsuits
Three offshore wind developers head to court after US ocean energy agency orders work halted. Vineyard Wind, already delivering power,...
offshorewind
Vineyard Wind Files for Preliminary Injunction in US Court
All five developers with offshore wind farms under construction in the US are now fighting the suspension order issued by the US Department...
wbur
Nantucket officials accuse offshore wind developer of going into hiding since Trump's election
Nantucket's select board gave Vineyard Wind two weeks to respond to a list of demands, including that it follow deadline requirements for...
pbs
Judge clears way for New York offshore wind project, handing industry another victory against Trump
District Judge Carl J. Nichols, an appointee of President Donald Trump, faulted the government for not responding to key points in Empire...
vineyardwind
Avangrid, CIP Announce First Power from Nation-Leading Vineyard Wind 1 Project
Developers complete early-stage commissioning work to deliver first ever power from offshore wind to Massachusetts.
mvtimes
Vineyard Wind completes construction
After a tumultuous construction process, Vineyard Wind 1 installed the last of its turbine blades on Friday evening.
utilitydive
With Vineyard Wind ruling, 4 of 5 offshore wind projects win relief from Trump freeze
Project developers said despite their outreach, the government “refused to discuss the supposedly new information about national security...
instituteforenergyresearch
New England Is Moving Ahead with Offshore Wind Facilities, Despite Their Cost
Vineyard Wind–a wind farm under construction off the coast of Massachusetts–has begun generating electricity from five of its planned 62...
nantucketcurrent
Vineyard Wind Makes Initial $4 Million Mitigation Payment To Nantucket
Nantucket Current is the island's leading online news source. We deliver the news, stories, and people of Nantucket, unbiased and...
latimes
Construction finishes on a major offshore wind farm, the first during Trump's tenure Construction is finished on a major Massachusetts offshore wind farm, the first project to reach this stage during President Trump’s time in office. Offshore construction was completed Friday night on Vineyard Wind with the installation of the final blades, Craig Gilvarg, a spokesperson for the project, said Saturday. Trump, who often talks about his dislike of wind power, has said his goal is to not let an...
wbur
Vineyard Wind, country's first large-scale offshore wind project, finishes construction After years of starts and stops, workers installed the final blades on the last turbine Friday evening to complete Vineyard Wind, the country's first large-scale offshore wind project. It will be at least several weeks until all 62 turbines in the wind farm off the coast of Massachusetts are fully up and running, generating power for the New England grid. Still, the end of construction is a milestone for t...
vineyardwind
Vineyard Wind 1 Nation’s first commercial-scale offshore wind project OVERVIEW Vineyard Wind is currently building the nation's first utility-scale offshore wind energy project over 15 miles off the coast of Massachusetts. The project will generate clean, renewable, affordable energy for over 400,000 homes and businesses across the Commonwealth, while reducing carbon emissions by over 1.6 million tons per year. LOCATION Vineyard Wind 1 is located in federal wind energy area OCS-A-050...
renews
Vineyard complete, Revolution delivers first power - reNews CIP and Iberdrola have completed turbine installation at the 800MW Vineyard Wind 1 off the US while Orsted and Skyborn have delivered first power from the 704MW Revolution Wind site (pictured). Industry group Oceantic Network said the milestones mark a significant advancement for the US offshore wind market, which currently has a single fully operational commercial-scale wind farm. The organisation added that Vineyard Wind 1 and five...
nytimes
Judge Revives Wind Farm That Trump Halted Off Martha’s Vineyard Climate|Judge Revives Wind Farm That Trump Halted Off Martha’s Vineyard https://www.nytimes.com/2026/01/27/climate/judge-offshore-wind-vineyard-massachusetts.html You have a preview view of this article while we are checking your access. When we have confirmed access, the full article content will load. A federal judge on Tuesday ruled that construction could continue on a $4.5 billion wind farm off the coast of Martha’s V...